Palm Boulevard

Districts 3 & 4 (3 Phases)



Project Managers


  • Daniel Salinas
  • Roy Villanueva

Funding Source


  • Capital Improvement Projects

Scope of Work


The project is planned for three phases. Basis for this consideration include school traffic, concrete curb repair, sidewalk construction and drainage improvements needed to be made. Roadway lanes will be milled 1-1.5 inches, followed by a 2-inch Type D Hotmix asphalt overlay with a 1-inch median overlay for uniformity.

Map Location

Aerial Map
Palm Boulevard Work

Budget Summary

Street Name Road Miles Estimated Cost Status
Phase 1 1.50 $180,000 Complete
Phase 2 1 $150,000 Pending
Phase 3 2.65 $425,000 Pending
Total 5.15 $755,000

Issues


  • Drainage improvements needed near Boca Chica Boulevard intersection and Fronton Street.
  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested for Phase 1: Passed
  • Phase 1 - Lane Closures only, Phase 2 - Road Closure
  • Railroad Comm notified of paving near tracks

Timeline


  • Phase 1: April 2012
  • Phase 2: April 2012 - May 2012
  • Phase 3: May 2012 - July 2012