Horseshoe Lake Subdivision

District 2



Project Managers


  • Daniel Salinas
  • Javier Rodriguez
  • Roy Villanueva

Funding Source


  • Community Development Block Grant

Scope of Work


The project repaired concrete curb and gutter on Armstrong Court, Cernan Court, Aldrin Court, and Lovell Court. Roadway edges were then milled, followed by a 2-inch Type D Hotmix asphalt overlay. Estimated time of completion, week of May 14-19.

Map Location

Aerial Map

Budget Summary


Street Name Miles Estimated Cost Status
Armstrong Court 0.30 $42,500 Complete
Cernan Court 0.25 $35,000 Complete
Shepard Court 0.20 $12,500 Complete
Glenn Court 0.20 $10,000 Complete
Aldrin Court 0.30 $40,000 Pending
Lovell Court 0.25 $30,000 Pending
Total 1.50 $170,000

Issues


  • Environmental assessments completed
  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested; Passed

Timeline


  • Concrete Work: April 2012 - May 2012
  • Milling/Preparation: April 2012 - May 2012
  • Paving: May 2012
Horseshoe Lake Subdivision Work 2