Hipp Street

District 2



Street Dimensions


  • 30 feet by 1,150 feet (0.25 road miles)

Project Managers


  • Daniel Salinas
  • Roy Villanueva

Funding Source


  • Capital Improvement Project Funding

Scope of Work


The project repaired 400 linear feet of concrete curb and gutter, then milled 1-1.5 inches off edge of roadway, followed by a 2-inch Type D Hotmix asphalt overlay.

Location


  • Renfro Boulevard - North Street

Budget Summary


Material Type
Amount Used
Estimated Cost
Concrete mix
22 cubic yards
$1,700
Emulsions
750 gallons
$2,200
Asphalt
400 tons
$25,000
  Total
$28,900

Issues


  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested; Passed

Timeline


  • Concrete Work: April 2012 - May 2012
  • Milling/Preparation: May 2012
  • Paving: May 2012