La Quinta Drive

District 1



Street Dimensions


  • 28 feet by 1,200 feet  (0.25 road miles)

Project Managers


  • Daniel Salinas
  • Roy Villanueva

Funding Source


  • Capital Improvement Project Funding
La Quinta Drive

Scope of Work


The project repaired 250 linear feet of concrete curb and gutter, then milled 1-1.5 inches off edge of roadway, followed by a 2-inch Type D Hotmix asphalt overlay.

Location


  • La Posada Drive to La Posada Drive
Budget Summary
Material Type
Amount Used
Estimated Cost
Concrete mix
14 cubic yards
$1,100
Emulsions
750 gallons
$500
Asphalt
400 tons
$25,000
  Total
$26,000

Issues


  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested; Passed
  • Environmental assessments completed

Timeline


  • Concrete Work: February 2012
  • Milling/Preparation: February 2012 - March 2012
  • Paving: March 2012