Fairwind Drive

District 2


 

Street Dimensions


  • 32 feet by 1,100 feet (0.25 road miles)

Project Managers


  • Daniel Salinas
  • Javier Rodriguez
  • Roy Villanueva

Funding Source


  • Capital Improvement Project Funding
Fairwind Drive

Scope of Work


The project repaired base at center of roadway. Roadway edges were then milled, followed by a 2-inch Type D Hotmix asphalt overlay.

Location


  • Alan A Dale Street to Robinhood Drive

Budget Summary


Material Type
Amount Used
Estimated Cost
Concrete mix
$1,200 square yards
$3,500
Emulsions
700 gallons
$2,000
Asphalt
400 tons
$24,000
  Total
$29,000

Issues


  • Environmental assessments completed
  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested; Passed
  • Geonetting installed for road base stabilizing

Timeline


  • Road Base Work: January 2012 - February 2012
  • Milling/Preparation: February 2012
  • Paving: February 2012 - March 2012