Hannah Drive

District 4



Street Dimensions


  • 28 feet by 1,100 feet (0.25 road miles)

Project Managers


  • Daniel Salinas
  • Javier Rodriguez
  • Roy Villanueva

Funding Source


  • Community Development Block Grant

Scope of Work


The project repaired approximately 20 linear feet of concrete work (curb, gutter, driveways) and partial drive-way. Roadway edges were then milled, followed by a two-inch Type D Hotmix asphalt overlay.

Location


  • Frontage Road to end of Roadway and to Soto Drive

Budget Summary


Material Type
Amount Used
Estimated Cost
Concrete mix
7 cubic yards
$532
Emulsions
685 gallons
$2,000
Asphalt
375 tons
$22,500
  Total
$25,032

Issues


  • Environmental Assessments completed
  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested; Passed
  • Repaired drive-way section at 57 Hannah Drive

Timeline


  • Concrete Work: January 2012
  • Milling/Preparation: January 2012 - February 2012
  • Paving: February 2012