Soto Drive

District 4



Street Dimensions


  • 28 feet by 1,226 feet (0.27 road miles)

Project Managers


  • Daniel Salinas
  • Javier Rodriguez
  • Roy Villanueva

Funding Source


  • Community Development Block Grant

Scope of Work


The project repaired approximately 750 linear feet of concrete work (curb, gutter, driveways) Roadway edges were then milled, a single-layer layer of #4 chipseal rock was applied and followed by a 2-inch Type D Hotmix asphalt overlay.

Location


  • Frontage Road to End of Roadway

Budget Summary


Material Type
Amount Used
Estimated Cost
Concrete mix
42 cubic yards
$3,192
Emulsions
1,120 gallons
$3,225
Asphalt
615 tons
$36,870

Total
$43,287

Issues


  • Environmental assessments completed
  • Utility spotting by Dig Test and BPUB
  • Asphalt quality tested; Passed

Timeline


  • Concrete Work: December 2011 - January 2012
  • Milling/Prep: January 2012
  • Paving: January 2012